Prakasha to Vinchur SH-7

RajpathInfracon    17-Dec-2021
Total Views |

Prakasha to Vinchur SH-7

Project Details

 
  • Name of Work
    Prakasha – Chadwel – Samoda – Vinchur Road (SH No. 7) in Km. 80/000 to 139/700 and Km. 154/200 to 174/400 and Section of the Bhabadbari to Sogras Phata (MDR No. 77) in Km. 0/000 to 7/000 (Total Length 86.90 Kms.), and Satana & Dahiwel Bypass in Nashik District
  • Principal Employer
    EE, Public Works Project Division, Malegaon.
  • Executed Cost (Rs. In Lakhs)
         11,000.00
  • Date of Work Order

         07/04/2011
  • Period

        18 Years & 7 Months (Including Concessio n Period)
  • Principal Features The B.O.T. project was taken over by Raj Group on 7/4/2011 & immediately started one toll station & another which was closed due to non-maintenance of 51 km stretch was started on 10/6/2011 after all renovation & maintenance work.


Prakasha to Vinchur SH-7